The Rhythm

Chandler/ Tempe, AZ

Project Overview
  • Mattamy Homes
  • April 2016 – Ongoing
  • $2,270,062
  • Project Overview: On this project, Mattamy Homes has selected DCS to be the general contractor for all offsite improvements on both Orchid Lane and Priest Drive, which include wet utility tie-ins, an overhead electrical conversion, and surface work tie-ins. Onsite work consist of more than 25,760 LF of underground utilities in sizes ranging from 3″ to 24″ in materials ranging from ductile iron pipe to vitrified clay pipe, along with a 96″ corrugated metal pipe underground retention system. Surface work includes more than 30,854 SY of asphalt pavement along with all signage, striping, and adjustment.