Dobson Road Improvements at Intel Driveways #1 and #4

Home Projects Dobson Road Improvements at Intel Driveways #1 and #4

Dobson Road Improvements at Intel Driveways #1 and #4

The purpose of this project was to increase capacity and access on Dobson Road to connect with onsite improvements at Intel Driveways #1 and #4. Driveway #1 is the northernmost Intel driveway on Dobson Road with an existing traffic signal. Driveway #4 is at Dobson Road and Chaparral Way, also a signalized intersection. Our scope of work included new turn lanes, restoration of raised landscaped median, re-striping, signage, curb, gutter, sidewalk, ADA upgrades, traffic signal upgrades, street lights, traffic signal interconnect, storm drainage, irrigation landscape restoration, and wet/dry utility improvements.

Project Details

  • Location:

    Chandler, AZ

  • Owner:

    City of Chandler

  • Engineer:

    Olsson

  • Delivery Method:

    Construction Manager at Risk (CMAR)

  • Value:

    $3.2M

  • Completed:

    Completed

  • Market:

    • Public Works