Higley and Baseline Intersection Improvements

PROJECT OVERVIEW

  • Year: 2012 – 2013
  • $2.6 Million
  • Project Overview: This project consisted of widening 1.5 miles of Higley and Baseline Roads. Work included removals, grading, paving 20,857 SY, concrete curb and gutter, water, 4,883 LF of 15” sewer, storm drain, microseal, 1,470 LF of 36” Roosevelt Water Conservation District (RWCD) irrigation and structures, SRP, street lights, traffic signal relocation, and landscaping.