Rivulon Infrastructure Improvements Project – Phase 1

PROJECT OVERVIEW

  • Nationwide Realty Investors
  • September 2014 – July 2015
  • $6.4 Million
  • Project Overview: This project consisted of widening Gilbert Road from the SanTan 202 freeway to Pecos Road, from four lanes to six lanes, complete with a median and the new construction of Rivulon Boulevard. This is one of the busiest sections of Gilbert Road. It required extensive traffic control and coordination between all stakeholders including the town of Gilbert, city of Chandler, and the Arizona Department of Transportation. DCS self-performed 65% of the project. Scope included grading 7,126 tons of asphalt paving, concrete, water, sewer, storm drain, landscaping, street lighting, and traffic signals.