Aloravita

PROJECT OVERVIEW

Aloravita Blvd Infrastructure Improvements & Jomax Road Widening

City of Peoria

May 2017 – September 2017

$3.3 Million

Project Overview:  This roadway and utility improvement project included a half mile widening of Jomax Road from a single lane of travel each direction to two lanes each direction with a flush median as well as the civil infrastructure for Aloravita, a 263 lot master planned community in Peoria . Scope of work included new sewer, water, dry utilities, asphalt paving, concrete curb and gutter, sidewalk, ADA ramps, storm drain, street lights and landscape improvements.

Tiger Mountain Drive and Victory Blvd

PROJECT OVERVIEW

  • DMB Associates, Inc.
  • March 2016 – Ongoing
  • $1,519,400
  • Project Overview: This project for DMB is the construction of two arterial roadways, which lead up to the newly constructed clubhouse located in the master community of Verrado. DCS is the general contractor for this project, and the scope of work includes the installation of two new arterial roadways, a double barrel 10’x8′ box culvert, dry utility installation, storm drain installation, and APS work along Indian School Road.